12 men and 20 women can do a construction work in 6 days. The ratio of work force of men to women is 5 : 4. Which of the following option is wrong to complete the same work in 3 days ?

20203M#mppsc-forest#pyq#mcq#2020
A.24 men and 40 women are employed
B.56 men are employed
C.70 women are employed
D.48 men are employedCorrect
Explanation & Solution

Correct Answer: (D) 48 men are employed

Using the given man-woman workforce ratio and total work calculation, 48 men working alone would take a different number of days, making option 4 incorrect for completing the work in 3 days.

हिंदी में प्रश्न एवं आदर्श उत्तर

12 आदमी और 20 औरतें एक निर्माण कार्य को 6 दिन में पूरा कर सकते हैं। आदमी से औरत की कार्यशक्ति का अनुपात 5 : 4 है। वही कार्य 3 दिन में समाप्त करने के लिए निम्नलिखित में से कौन-सा पर्याय गलत है ?

A.24 आदमी और 40 औरतें काम पर लगाई जाएँ
B.56 आदमी काम पर लगाए जाएँ
C.70 औरतें काम पर लगाई जाएँ
D.48 आदमी काम पर लगाए जाएँसही

सही उत्तर: (D) 48 आदमी काम पर लगाए जाएँ

दिए गए कार्यबल अनुपात और कुल कार्य की गणना के अनुसार, 48 आदमियों को काम पर लगाना 3 दिन में कार्य पूरा करने के लिए गलत विकल्प है।

See this question in context →