The East-West corridor of the Golden Quadrilateral connects which of the following centers (nodes)?
Explanation & Solution
The correct answer is (A) Silchar and Porbandar.
- East-West Corridor (NHDP Phase II): As part of the National Highways Development Project (NHDP) managed by NHAI, the East-West Corridor spans approximately 3,300 km of 4/6 lane highway connecting Silchar (Assam) in the east to Porbandar (Gujarat) on the western coast.
- Intersection with North-South Corridor: The North-South Corridor (Srinagar to Kanyakumari) and East-West Corridor (Silchar to Porbandar) intersect at Jhansi (Uttar Pradesh), adjacent to Madhya Pradesh.
- Option Breakdown:
- (B) Guwahati and Ahmedabad: Major transit hubs along the alignment, but not the terminal nodes.
- (C) Kandla and Tinsukia: Important ports/railheads, not the designated corridor endpoints.
- (D) Itanagar and Jamnagar: State capitals/refinery hubs, not endpoints of the NHDP E-W corridor.
हिंदी में प्रश्न एवं आदर्श उत्तर
स्वर्णिम चतुर्भूज का पूर्वी-पश्चिम गलियारा निम्नलिखित में से किन केन्द्रों (नाभिक) को जोड़ती है?
सही उत्तर (A) सिल्चर एवं पोरबन्दर को है।
- पूर्व-पश्चिम गलियारा (NHDP चरण II): भारतीय राष्ट्रीय राजमार्ग प्राधिकरण (NHAI) की राष्ट्रीय राजमार्ग विकास परियोजना के अंतर्गत पूर्व-पश्चिम गलियारा पूर्व में सिल्चर (असम) को पश्चिम में पोरबंदर (गुजरात) से जोड़ता है। इसकी कुल लंबाई लगभग 3,300 किमी है।
- उत्तर-दक्षिण गलियारे से मिलन: उत्तर-दक्षिण गलियारा (श्रीनगर से कन्याकुमारी) और पूर्व-पश्चिम गलियारा (सिल्चर से पोरबंदर) मध्य प्रदेश की सीमा के निकट झाँसी (उत्तर प्रदेश) में एक-दूसरे को काटते हैं।
- विकल्पों का विश्लेषण:
- (B) गुवाहाटी एवं अहमदाबाद: इस मार्ग के प्रमुख शहर हैं, किंतु अंतिम छोर (टर्मिनल नोड्स) नहीं हैं।
- (C) काण्डला एवं तिनसुकिया: बंदरगाह/रेलवे जंक्शन हैं, कॉरिडोर के छोर नहीं।
- (D) ईटानगर एवं जामनगर: यह इस राष्ट्रीय गलियारे के घोषित छोर नहीं हैं।