A contract on construction job specifies a penalty for delay in completion of the work beyond a certain date is as follows: Rs. 200 for the first day, Rs. 250 for the second day, Rs. 300 for the third day etc., the penalty for each succeeding day being 50 more than that of the preceding day. How much penalty should the contractor pay if he delays the work by 10 days?

20113Mprelimsupscyear-2011p2quantitative-abilitylinear-equation
A.Rs. 4950
B.Rs. 4250Correct
C.Rs. 3600
D.Rs. 650
Explanation & Solution

Correct Option: (B) Rs. 4250

Penalty sequence: 200, 250, 300, 350, 400, 450, 500, 550, 600, 650. Sum = 10(200 + 650)/2 = 4250 (arithmetic sequence with a=200, d=50, n=10).

हिंदी में प्रश्न एवं आदर्श उत्तर

निर्माण कार्य पर एक अनुबंध में निर्दिष्ट समयसीमा के बाद कार्य पूरा करने में देरी पर जुर्माना इस प्रकार है: पहले दिन के लिए Rs. 200, दूसरे दिन के लिए Rs. 250, प्रत्येक अगले दिन का जुर्माना पिछले दिन से 50 अधिक होगा। अगर ठेकेदार काम में 10 दिन की देरी करता है तो उसे कितना जुर्माना भरना होगा?

A.रु. 4950
B.रु. 4250सही
C.रु. 3600
D.रु. 650

सही उत्तर: (B) रु. 4250

दंड क्रम: 200, 250, 300, 350, 400, 450, 500, 550, 600, 650। जोड़ = 10(200 + 650)/2 = 4250 (बीजगणितीय क्रम जिसमें a=200, d=50, n=10)।